In this part of the report, we provide a detailed information overview.
Focus on facilitating the energy transition
2024 |
2023 |
2022 |
2021 |
2020 |
|
The grids |
|||||
Section lengths (x 1,000 km) |
|||||
Electricity grid |
147.7 |
146.3 |
144.9 |
143.5 |
142.2 |
- Low voltage |
100.1 |
99.2 |
98.5 |
97.6 |
96.9 |
- Medium voltage |
47.5 |
47 |
46.3 |
45.8 |
45.2 |
- Intermediate voltage |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Gas grid |
46.1 |
46.1 |
46.2 |
46.3 |
46.3 |
- Low pressure |
37.4 |
37.4 |
37.5 |
37.5 |
37.5 |
- High pressure |
8.7 |
8.7 |
8.7 |
8.8 |
8.8 |
Stations (x 1,000) |
|||||
E-stations |
58.0 |
56.9 |
57.2 |
56.6 |
55.7 |
G-stations |
21.2 |
21.5 |
21.9 |
22.0 |
22.4 |
Distribution Automation (DA)-stations1 |
395 |
428 |
544 |
657 |
390 |
Distribution Automation Light (DALI)-stations1 |
4,679 |
6,038 |
4,249 |
3,544 |
3,531 |
Number of connections (x 1,000) |
|||||
Electricity |
2,997 |
2,966 |
2,941 |
2,911 |
2,880 |
- Domestic (including 3x25 A) |
2,729 |
2,706 |
2,683 |
2,661 |
2,640 |
- Low-voltage connections other (small-volume as from 3x25A) |
249 |
242 |
240 |
233 |
223 |
- Medium voltage connections |
19 |
18 |
18 |
17 |
17 |
Gas |
2,269 |
2,285 |
2,303 |
2,315 |
2,324 |
- Domestic (G4 and G6) |
2,217 |
2,232 |
2,248 |
2,259 |
2,266 |
- Low pressure other (small-volume as from G10) |
49 |
50 |
52 |
53 |
55 |
- High pressure connections |
3 |
3 |
3 |
3 |
3 |
Transported quantities |
|||||
Electricity (GWh) |
33,110 |
30,893 |
30,991 |
31,989 |
31,176 |
Gas (Mm3) |
4,229 |
4,244 |
4,714 |
6,172 |
5,636 |
Of which green gas |
118 |
99 |
76 |
77 |
63 |
Product quality |
|||||
Outage time electricity (in minutes) |
22.5 |
20.0 |
14.0 |
17.6 |
13.0 |
- High voltage |
0.5 |
0.8 |
0.5 |
0.7 |
0.01 |
- Medium voltage |
13.9 |
11.3 |
7.7 |
11.1 |
7.4 |
- Low voltage |
8.0 |
7.8 |
5.8 |
5.8 |
5.6 |
Outage time gas (in seconds) |
56 |
137 |
109 |
75 |
81 |
Laws and regulations
The Administrative and Legal Affairs & Digital Security departments and other relevant departments have not received any other fines with regard to services provided by Enexis or for non-compliance with the Energy Act, the Gas Act, or environmental laws. Furthermore, there were no occurrences for which non-monetary sanctions were imposed.