Off-balance sheet commitments and assets

Long-term financial liabilities

Long-term financial liabilities amounted to € 847 million as at 30 June 2025 (year-end 2024: € 791 million).

30 June 2025

31 December 2024

€ Million

< 1 year

1-5 year

> 5 year

< 1 year

1-5 year

> 5 year

Service agreements

17

9

-

18

18

-

IT

41

50

0

49

71

0

Costs for grid losses1

122

285

43

120

212

44

Investment and financing obligation

6

1

-

10

3

-

Materials and services

156

91

26

138

73

35

Total

342

436

69

335

377

79

  • 1As at the 30 June 2025, 100% electricity and 100% gas was covered for 2026. Purchasing for the next regulatory period from 2027 has started. The projected demand for 2027 has been purchased for electricity at over 70% and for gas at over 30%, with the purchased volume gradually decreasing in the following years.
  • The above table shows the legally binding financial commitments. However, our procurement expectations for materials and services are considerably higher. Enexis enters into framework agreements with multiple suppliers for the procurement of essential materials and services, including cables, transformers and contractor work. These framework agreements do not contain any legal purchase obligations and are the result of large-scale tendering processes. The total value of these contracts can amount to several billion euros over their entire term, in line with our commitment to the energy transition.

    Obligation regarding the removal of gas connections at the request of customers

    Under the Gas Act, Enexis is obliged to remove gas connections if the customer submits a request for this. If the customer specifies a desired date for the removal of the connection, Enexis may charge the customer for the costs. For requests without a desired date, these costs will be covered in (future) tariffs.

    As of the end of June 2025, Enexis has formed a provision of € 8 million for the expected removal costs of requests without a desired date that were received on or before the balance sheet date that will be carried out after the balance sheet date.

    No provision has been made for future removal requests. Depending on factors such as the speed of the energy transition, design choices for the new energy system, and developments in legislation and regulations, future requests for removal may result in a significant outflow of funds in future periods. However, the principle of tariff regulation is that regional grid operators are compensated for their (efficient) costs and investments, including a reasonable return. Under the current regulatory method, Enexis will be reimbursed for these removal costs via the tariffs two years later. While the total removal cost over the period up to and including 2050 may be significant, its impact on Enexis’s financial position is expected to be limited as these costs will be reimbursed via regulated tariffs.